| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4030-04 | ELABORACION DE CONCRETO HIDRAULICO F'c=200 KG/CM2 HECHO EN OBRA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.335000 | $2,378.40 | $796.76 |
| ARENA M ALEMAN 1 | ARENA MIGUEL ALEMAN | M3 | 0.560000 | $315.00 | $176.40 |
| GRAVA M ALEMAN 1 | GRAVA MIGUEL ALEMAN | M3 | 0.625000 | $310.00 | $193.75 |
| AGUA ADQUIRIDA 1 | AGUA ADQUIRIDA | M3 | 0.200000 | $31.50 | $6.30 |
| Suma de Material | $1,173.21 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006940 | $307.31 | $2.13 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.069440 | $251.32 | $17.45 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.069440 | $197.97 | $13.75 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.416670 | $185.16 | $77.15 |
| Suma de Mano de Obra | $110.48 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $110.48 | $3.31 |
| Suma de Herramienta | $3.31 | ||||
| Equipo | |||||
| REVOLVEDORA 1 SACO 1 | REVOLVEDORA KOHLER R-10 DE 1 SACO MOTOR GASOLINA DE 8 HP | HORA | 0.444440 | $49.38 | $21.95 |
| CAMION PLATAF 6.8T 1 | CAMION PLATAFORMA FORD DE 6.8 TON DE CAPACIDAD | HORA | 0.055560 | $241.47 | $13.42 |
| Suma de Equipo | $35.37 | ||||
| Costo Directo | $1,322.37 |