| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4003-08 | CIMENTACION A BASE DE ZAPATA CORRIDA DE 40 x 90 CM, FABRICACION DE CONCRETO F'c=200 KG/CM2, ARMADO CON Vs # 3 @ 18 CM INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 14.000000 | $16.15 | $226.10 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.280000 | $34.00 | $9.52 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.120000 | $19.00 | $2.28 |
| DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 4.000000 | $2.50 | $10.00 |
| Suma de Material | $256.92 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.015000 | $307.31 | $4.61 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.150000 | $251.32 | $37.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.150000 | $197.97 | $29.70 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.150000 | $185.16 | $27.77 |
| Suma de Mano de Obra | $99.78 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $99.78 | $2.99 |
| Suma de Herramienta | $2.99 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 4.800000 | $23.47 | $112.66 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.360000 | $1,322.37 | $476.05 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.360000 | $230.70 | $83.05 |
| Suma de Auxiliar | $671.76 | ||||
| Costo Directo | $1,031.45 |