| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-78 | SUMINISTRO E INSTALACION DE POLIN DE APOYO DE 1/2" DE ESPESOR EN UNION DE MARCOS SOBRE COLUMNAS INCLUYE HABILITADO Y MONTAJE | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| POLIN 4" X 6.44 KG/M | POLIN DE 4" x 6.44 KG/M PINTADO | KG | 1.100000 | $14.80 | $16.28 |
| ACETILENO 1 | ACETILENO | KG | 0.015000 | $130.00 | $1.95 |
| OXIGENO 1 | OXIGENO | M3 | 0.020000 | $39.00 | $0.78 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.025000 | $49.88 | $1.25 |
| Suma de Material | $20.26 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001000 | $307.31 | $0.31 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.010000 | $251.32 | $2.51 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.010000 | $197.97 | $1.98 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.010000 | $185.16 | $1.85 |
| Suma de Mano de Obra | $6.65 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $6.65 | $0.20 |
| Suma de Herramienta | $0.20 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.030000 | $113.61 | $3.41 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.030000 | $26.43 | $0.79 |
| Suma de Equipo | $4.20 | ||||
| Costo Directo | $31.31 |