| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4130-07 | SOBREPRECIO POR ACABADO PULIDO EN LOSAS Y MUROS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.250000 | $16.15 | $4.04 |
| Suma de Material | $4.04 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007100 | $307.31 | $2.18 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.071400 | $251.32 | $17.94 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.071400 | $197.97 | $14.14 |
| Suma de Mano de Obra | $34.26 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $34.26 | $1.03 |
| Suma de Herramienta | $1.03 | ||||
| Auxiliar | |||||
| MOR CEM ARE 1:4 1 | MORTERO CEMENTO ARENA 1:4 | M3 | 0.015000 | $1,324.75 | $19.87 |
| Suma de Auxiliar | $19.87 | ||||
| Costo Directo | $59.20 |