Clave | Descripción del Análisis de Precio Unitario | Unidad |
4080-10 | CIMBRA ACABADO APARENTE EN TRABE CON TRIPLAY DE 16 MM INCLUYE HABILITADO, CIMBRADO Y DESCIMBRADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TRIPLAY 16 MM 1 | TRIPLAY DE PINO DE 16 MM DE ESPESOR | M2 | 0.140000 | $112.00 | $15.68 |
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 4.700000 | $16.15 | $75.91 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.200000 | $34.00 | $6.80 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 1.100000 | $2.50 | $2.75 |
Suma de Material | $108.68 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.013160 | $307.31 | $4.04 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.131580 | $251.32 | $33.07 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.131580 | $197.97 | $26.05 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.065790 | $185.16 | $12.18 |
Suma de Mano de Obra | $75.34 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $75.34 | $2.26 |
Suma de Herramienta | $2.26 | ||||
Equipo | |||||
CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.021050 | $202.91 | $4.27 |
Suma de Equipo | $4.27 | ||||
Costo Directo | $190.55 |