Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-45 | SUMINISTRO Y COLOCACION DE COLUMNA METALICA (A-36) DE 91.5 CM DE LONGITUD FORMADAS POR: (TIPO I SOBRE PEDESTAL Y MURO ANCHO) INCLUYE HABILITADO Y MONTAJE | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
ANGULO 3/8″X3″X3″ 1 | ANGULO DE 3″ x 3″ x 3/8″ | KG | 434.000000 | $20.00 | $8,680.00 |
SOLERA 3″*3/8″ 1 | SOLERA 3″ x 3/8″ | KG | 178.000000 | $16.00 | $2,848.00 |
PLACA DE ACERO 1/2″1 | PLACA DE ACERO DE 1/2″ | KG | 363.000000 | $12.50 | $4,537.50 |
ACETILENO 1 | ACETILENO | KG | 23.310000 | $130.00 | $3,030.30 |
OXIGENO 1 | OXIGENO | M3 | 31.080000 | $39.00 | $1,212.12 |
SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 38.850000 | $49.88 | $1,937.84 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 5.439000 | $90.00 | $489.51 |
Suma de Material | $22,735.27 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 1.400000 | $307.31 | $430.23 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 14.000000 | $251.32 | $3,518.48 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 14.000000 | $197.97 | $2,771.58 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 14.000000 | $185.16 | $2,592.24 |
Suma de Mano de Obra | $9,312.53 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $9,312.53 | $279.38 |
Suma de Herramienta | $279.38 | ||||
Equipo | |||||
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 23.000000 | $113.61 | $2,613.03 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 23.000000 | $26.43 | $607.89 |
CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 6.000000 | $285.24 | $1,711.44 |
Suma de Equipo | $4,932.36 | ||||
Auxiliar | |||||
APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 15.000000 | $129.42 | $1,941.30 |
Suma de Auxiliar | $1,941.30 | ||||
Costo Directo | $39,200.84 |