| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-61 | FABRICACION E INSTALACION DE ESCALERA TIPO MARINA PARA ACCESO A INTERIOR DE CISTERNA FABRICADA CON PERFILES DE ACERO A-36 INCLUYE RECUBRIMIENTO CON PRIMARIO CROMATO DE ZINC Y ACABADO ESMALTE | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| POLIN 12" X 3 1/2" 1 | POLIN DE 12" x 3 1/2" PINTADO | KG | 1.100000 | $14.70 | $16.17 |
| ACETILENO 1 | ACETILENO | KG | 0.030000 | $130.00 | $3.90 |
| OXIGENO 1 | OXIGENO | M3 | 0.040000 | $39.00 | $1.56 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.050000 | $49.88 | $2.49 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.007000 | $90.00 | $0.63 |
| Suma de Material | $24.75 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001750 | $307.31 | $0.54 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.017500 | $251.32 | $4.40 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.017500 | $197.97 | $3.46 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.017500 | $185.16 | $3.24 |
| Suma de Mano de Obra | $11.64 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $11.64 | $0.35 |
| Suma de Herramienta | $0.35 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.030000 | $113.61 | $3.41 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.030000 | $26.43 | $0.79 |
| CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.008000 | $285.24 | $2.28 |
| Suma de Equipo | $6.48 | ||||
| Costo Directo | $43.22 |