Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-46 | SUMINISTRO Y COLOCACION DE COLUMNA METALICA (A-36) DE 91.5 CM DE LONGITUD FORMADAS POR: (TIPO II SOBRE MURO ANGOSTO) INCLUYE HABILITADO Y MONTAJE | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
ANGULO 3/8″X3″X3″ 1 | ANGULO DE 3″ x 3″ x 3/8″ | KG | 158.000000 | $20.00 | $3,160.00 |
SOLERA 3″*3/8″ 1 | SOLERA 3″ x 3/8″ | KG | 65.000000 | $16.00 | $1,040.00 |
PLACA DE ACERO 1/2″1 | PLACA DE ACERO DE 1/2″ | KG | 136.000000 | $12.50 | $1,700.00 |
ACETILENO 1 | ACETILENO | KG | 6.660000 | $130.00 | $865.80 |
OXIGENO 1 | OXIGENO | M3 | 8.880000 | $39.00 | $346.32 |
SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 11.100000 | $49.88 | $553.67 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 1.554000 | $90.00 | $139.86 |
Suma de Material | $7,805.65 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.400000 | $307.31 | $122.92 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 4.000000 | $251.32 | $1,005.28 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 4.000000 | $197.97 | $791.88 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 4.000000 | $185.16 | $740.64 |
Suma de Mano de Obra | $2,660.72 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $2,660.72 | $79.82 |
Suma de Herramienta | $79.82 | ||||
Equipo | |||||
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 6.000000 | $113.61 | $681.66 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 6.000000 | $26.43 | $158.58 |
CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 1.500000 | $285.24 | $427.86 |
Suma de Equipo | $1,268.10 | ||||
Auxiliar | |||||
APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 5.400000 | $129.42 | $698.87 |
Suma de Auxiliar | $698.87 | ||||
Costo Directo | $12,513.16 |