| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 05-6190 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL VACIADO CON BOMBA F'C=350 KG/CM2 REVENIMIENTO DE 14 CM AGREGADO MAXIMO 1 1/2" EN COLUMNAS Y MUROS | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0900-68 | CONC. PREMEZCLADO RN F'C=350 KG/CM2 AGREGADO MAX.1 1/2" (A) | M3 | 1.040000 | $1,843.93 | $1,917.69 |
| 0901-02 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(B) | M3 | 1.040000 | $95.40 | $99.22 |
| 0601-05 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 1.040000 | $223.82 | $232.77 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.060000 | $18.39 | $1.10 |
| Suma de Material | $2,250.78 | ||||
| Mano de Obra | |||||
| 02-0450 | CUADRILLA No 45 ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.055500 | $1,881.35 | $104.41 |
| Suma de Mano de Obra | $104.41 | ||||
| Equipo | |||||
| 03-4010 | VIBRADOR DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HORA | 0.444400 | $6.55 | $2.91 |
| Suma de Equipo | $2.91 | ||||
| Costo Directo | $2,358.10 |