| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-1610 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 20 X 15 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 20 - 4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.789000 | $12.74 | $22.79 |
| 0111-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 20 - 4 | M | 1.050000 | $25.50 | $26.78 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $14.23 | $2.85 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $18.93 | $2.56 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
| Suma de Material | $58.23 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.105200 | $756.84 | $79.62 |
| Suma de Mano de Obra | $79.62 | ||||
| Concepto | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $912.50 | $28.74 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.105200 | $22.08 | $2.32 |
| Suma de Concepto | $31.06 | ||||
| Costo Directo | $168.91 |