| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-0270 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 20 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 20-4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.196000 | $12.74 | $15.24 |
| 0111-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 20 - 4 | M | 1.050000 | $25.50 | $26.78 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $18.93 | $2.56 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
| Suma de Material | $50.69 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.074000 | $756.84 | $56.01 |
| Suma de Mano de Obra | $56.01 | ||||
| Concepto | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $912.50 | $28.74 |
| Suma de Concepto | $28.74 | ||||
| Costo Directo | $135.44 |