Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-1260 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 12 X 20 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON ARMEX DE 12 X 20 – 4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106000 | $12.74 | $14.09 |
0115-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 12 X 20 – 4 | M | 1.050000 | $19.46 | $20.43 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $18.93 | $2.37 |
0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
Suma de Material | $41.91 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.085100 | $756.84 | $64.41 |
Suma de Mano de Obra | $64.41 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.025200 | $981.58 | $24.74 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.085100 | $22.08 | $1.88 |
Suma de Concepto | $26.62 | ||||
Costo Directo | $132.94 |