Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-0330 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIEMBRA SECCION=15 X 25 CM, CONCRETO F’C=150 KG/CM2-3/4″, REFORZADA CON ARMEX DE 15 X 25-4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.196000 | $12.74 | $15.24 |
0112-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 25 – 4 | M | 1.050000 | $28.60 | $30.03 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.948700 | $14.30 | $13.57 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.200000 | $18.93 | $3.79 |
0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
Suma de Material | $65.88 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.075400 | $756.84 | $57.07 |
Suma de Mano de Obra | $57.07 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.039300 | $912.50 | $35.86 |
Suma de Concepto | $35.86 | ||||
Costo Directo | $158.81 |