| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-1150 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 10 X 25 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON 4 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 30 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $12.74 | $14.09 |
| 0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 2.339400 | $10.43 | $24.40 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.843300 | $12.55 | $10.58 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $18.93 | $2.37 |
| 0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
| Suma de Material | $56.46 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.097500 | $756.84 | $73.79 |
| Suma de Mano de Obra | $73.79 | ||||
| Concepto | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.026200 | $912.50 | $23.91 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.097500 | $22.08 | $2.15 |
| Suma de Concepto | $26.06 | ||||
| Costo Directo | $156.31 |