Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-5730 | CASTILLO DE CONCRETO SECCION= 12 X 25 CM, CONCRETO F’C=150 KG/CM2-3/4″, CIMBRA 2 CARAS, REFORZADO CON ARMEX DE 12 X 25 – 4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106000 | $12.74 | $14.09 |
0116-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 12 X 25 – 4 | M | 1.050000 | $20.86 | $21.90 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $18.93 | $2.37 |
0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
Suma de Material | $43.38 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.086900 | $756.84 | $65.77 |
Suma de Mano de Obra | $65.77 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.031500 | $912.50 | $28.74 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.086900 | $22.08 | $1.92 |
Suma de Concepto | $30.66 | ||||
Costo Directo | $139.81 |