| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-5890 | CASTILLO DE CONCRETO SECCION= 15 X 20 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 2 CARAS, REFORZADO CON 4 VARILLAS A.R. DE 5/16" ESTRIBOS DE 1/4" A/C 25 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.196000 | $12.74 | $15.24 |
| 0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16") | KG | 1.612800 | $12.58 | $20.29 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.843300 | $12.55 | $10.58 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $18.93 | $2.56 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
| Suma de Material | $54.78 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.114200 | $756.84 | $86.43 |
| Suma de Mano de Obra | $86.43 | ||||
| Concepto | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.031500 | $912.50 | $28.74 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.114200 | $22.08 | $2.52 |
| Suma de Concepto | $31.26 | ||||
| Costo Directo | $172.47 |