Clave | Descripción del Análisis de Precio Unitario | Unidad |
40-1400 | SUMINISTRO Y COLOCACION DE COPLE DE BRONCE PARA CONEXION INTERIOR COBRE A ROSCA INTERIOR 10 MM | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
3004-76 | COPLE DE BRONCE P/CONEX.INT.COBRE A ROSCA INT.10 MM | PZA | 1.030000 | $16.65 | $17.15 |
3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.003800 | $33.60 | $0.13 |
3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.000900 | $52.30 | $0.05 |
3037-34 | GASOLINA BLANCA | LT | 0.031000 | $7.82 | $0.24 |
1502-70 | SEGUETA DE ACERO | PZA | 0.014200 | $7.94 | $0.11 |
3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.011000 | $4.08 | $0.04 |
3035-52 | CINTA TEFLON DE 13 MM | M | 0.055000 | $3.57 | $0.20 |
Suma de Material | $17.92 | ||||
Mano de Obra | |||||
02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.045400 | $802.68 | $36.44 |
Suma de Mano de Obra | $36.44 | ||||
Costo Directo | $54.36 |