Clave | Descripción del Análisis de Precio Unitario | Unidad |
03-2090 | CONCRETO HECHO EN OBRA F’C=250 KG/CM2, RESISTENCIA RAPIDA, AGREGADO MAXIMO 3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.412000 | $1,694.85 | $698.28 |
0302-20 | ARENA | M3 | 0.535000 | $157.59 | $84.31 |
0302-30 | GRAVA | M3 | 0.637000 | $157.59 | $100.38 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.243000 | $18.39 | $4.47 |
0173-55 | FESTERMIX R.R. | CUB | 0.433600 | $271.41 | $117.68 |
Suma de Material | $1,005.12 | ||||
Mano de Obra | |||||
02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
Suma de Mano de Obra | $162.69 | ||||
Equipo | |||||
03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
Suma de Equipo | $5.55 | ||||
Costo Directo | $1,173.36 |