| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-0120 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=10 X 15 CM, CONCRETO F'C=200 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 10-4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $12.74 | $14.09 |
| 0109-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 10-4 | M | 1.050000 | $22.05 | $23.15 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $18.93 | $2.37 |
| 0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
| Suma de Material | $44.63 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.070100 | $756.84 | $53.05 |
| Suma de Mano de Obra | $53.05 | ||||
| Concepto | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.015700 | $981.58 | $15.41 |
| Suma de Concepto | $15.41 | ||||
| Costo Directo | $113.09 |