Clave | Descripción del Análisis de Precio Unitario | Unidad |
09-2670 | PISO DE CONCRETO EN CUADROS ARISTAS REMATADAS CON VOLTEADOR CUADROS DE 2.50 X 2.50 MESPESOR=10 CM CONCRETO HECHO EN OBRA F’C=200 KG/CM2-3/4″ REFUERZO=MALLA 66-1010 ACABADO=SIN ACABADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $14.39 | $14.68 |
Suma de Material | $16.37 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.166600 | $756.84 | $126.09 |
Suma de Mano de Obra | $126.09 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.104000 | $981.58 | $102.08 |
Suma de Concepto | $102.08 | ||||
Costo Directo | $244.54 |