| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2030 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA RAPIDA, AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.273000 | $1,694.85 | $462.69 |
| 0302-20 | ARENA | M3 | 0.542000 | $157.59 | $85.41 |
| 0302-30 | GRAVA | M3 | 0.656000 | $157.59 | $103.38 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.271000 | $18.39 | $4.98 |
| 0173-55 | FESTERMIX R.R. | CUB | 0.287300 | $271.41 | $77.98 |
| Suma de Material | $734.44 | ||||
| Mano de Obra | |||||
| 02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
| Suma de Mano de Obra | $162.69 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
| Suma de Equipo | $5.55 | ||||
| Costo Directo | $902.68 |