Clave | Descripción del Análisis de Precio Unitario | Unidad |
09-2710 | PISO DE CONCRETO EN CUADROS ARISTAS REMATADAS CON VOLTEADOR CUADROS DE 2.50 X 2.50 M ESPESOR=10 CM CONCRETO PREMEZCLADO F’C=200 KG/CM2-3/4″ REFUERZO=MALLA 66-1010 ACABADO=ESCOBILLADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0900-08 | CONCRETO PREMEZC.RN F’C=200 KG/CM2 AGREGADO MAXIMO 3/4″ (A) | M3 | 0.104000 | $1,665.94 | $173.26 |
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $14.39 | $14.68 |
Suma de Material | $189.63 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.173900 | $756.84 | $131.61 |
Suma de Mano de Obra | $131.61 | ||||
Costo Directo | $321.24 |