| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 20-0200 | RIEGO DE SELLO SOBRE CARPETA ASFALTICO (NO INCLUYE 1.00 KG DE CEMENTO POR M2 Y LIMPIEZA) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.003000 | $18.39 | $0.06 |
| Suma de Material | $1.75 | ||||
| Mano de Obra | |||||
| 02-0010 | CUADRILLA No 1 ( 1 PEON ) | JOR | 0.003000 | $286.73 | $0.86 |
| Suma de Mano de Obra | $0.86 | ||||
| Costo Directo | $2.61 |