Clave | Descripción del Análisis de Precio Unitario | Unidad |
03-2110 | CONCRETO HECHO EN OBRA F’C=300 KG/CM2, RESISTENCIA RAPIDA, AGREGADO MAXIMO 3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.442000 | $1,694.85 | $749.12 |
0302-20 | ARENA | M3 | 0.540000 | $157.59 | $85.10 |
0302-30 | GRAVA | M3 | 0.655600 | $157.59 | $103.32 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.245000 | $18.39 | $4.51 |
0173-55 | FESTERMIX R.R. | CUB | 0.465200 | $271.41 | $126.26 |
Suma de Material | $1,068.31 | ||||
Mano de Obra | |||||
02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
Suma de Mano de Obra | $162.69 | ||||
Equipo | |||||
03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
Suma de Equipo | $5.55 | ||||
Costo Directo | $1,236.55 |