Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-1810 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 28 X 15 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS R.N. DE 3/8″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 2.050000 | $12.74 | $26.12 |
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 2.339400 | $10.43 | $24.40 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 1.012000 | $12.55 | $12.70 |
0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $14.23 | $2.85 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $18.93 | $2.56 |
0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
Suma de Material | $71.88 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.160000 | $756.84 | $121.09 |
Suma de Mano de Obra | $121.09 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.044100 | $981.58 | $43.29 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.160000 | $22.08 | $3.53 |
Suma de Concepto | $46.82 | ||||
Costo Directo | $239.79 |