Clave | Descripción del Análisis de Precio Unitario | Unidad |
03-2160 | CONCRETO HECHO EN OBRA F’C=100 KG/CM2, RESISTENCIA RAPIDA, AGREGADO MAXIMO 1 1/2″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.258000 | $1,694.85 | $437.27 |
0302-20 | ARENA | M3 | 0.462000 | $157.59 | $72.81 |
0302-30 | GRAVA | M3 | 0.754000 | $157.59 | $118.82 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.262000 | $18.39 | $4.82 |
0173-55 | FESTERMIX R.R. | CUB | 0.271500 | $271.41 | $73.69 |
Suma de Material | $707.41 | ||||
Mano de Obra | |||||
02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
Suma de Mano de Obra | $162.69 | ||||
Equipo | |||||
03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
Suma de Equipo | $5.55 | ||||
Costo Directo | $875.65 |