| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-7360 | CASTILLO DE CONCRETO AHOGADO EN MURO DE BLOCK O TABIQUE DE PERF. VERTICAL MURO DE 12 CM (EN 3 HUECOS) CONC. F'C=200 KG/CM2-3/4" REF. CON 3 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 2 HILADAS | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 1.752000 | $10.43 | $18.27 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.312000 | $12.55 | $3.92 |
| Suma de Material | $22.19 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.062500 | $756.84 | $47.30 |
| Suma de Mano de Obra | $47.30 | ||||
| Concepto | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.021000 | $981.58 | $20.61 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.031200 | $22.08 | $0.69 |
| Suma de Concepto | $21.30 | ||||
| Costo Directo | $90.79 |