Clave | Descripción del Análisis de Precio Unitario | Unidad |
70-1570 | SUMINISTRO FABRICACION Y MONTAJE DE VENTEOS EN TANQUES DE CUPULA FIJA (INCLUYE CORTE EN CUPULA DE TANQUE.) | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0128-16 | PLACA DE ACERO ESTRUCTURAL | KG | 50.000000 | $14.99 | $749.50 |
0950-25 | GAS OXIGENO | M3 | 0.500000 | $46.20 | $23.10 |
0950-20 | GAS ACETILENO | KG | 0.050000 | $159.17 | $7.96 |
1551-35 | SOLDADURA E-6010 DE 1/8″ | KG | 1.630000 | $65.09 | $106.10 |
2600-96 | PINTURA PRIMARIA RP-2 CROMATO DE ZINC | LT | 0.230000 | $70.32 | $16.17 |
2600-86 | PINTURA ESMALTE ALQUIDALICO RA-20 | LT | 0.340000 | $30.21 | $10.27 |
2600-97 | PINTURA PRIMARIA RP-3 INORGANICA DE ZINC | LT | 0.270000 | $121.15 | $32.71 |
2600-98 | SOLUCION CURADORA PARA RP-3 | LT | 0.400000 | $41.23 | $16.49 |
0309-10 | HAMACA CON CABLE HASTA 30 M | R/D | 2.000000 | $133.63 | $267.26 |
Suma de Material | $1,229.56 | ||||
Mano de Obra | |||||
02-0800 | CUADRILLA No 80 ( 1 SOLDADOR CALIFICADO + 2 AYUDANTES DE SOLDADOR ) | JOR | 1.800000 | $1,135.24 | $2,043.43 |
Suma de Mano de Obra | $2,043.43 | ||||
Equipo | |||||
03-4210 | SOLDADOR DE ARCO ELECTRICO MILLER MODELO M1250 CD TRANSFORMADOR RECTIFICADOR | HORA | 5.810000 | $1.46 | $8.48 |
03-4220 | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HORA | 5.810000 | $0.56 | $3.25 |
03-4321 | EQUIPO PARA APLICACION DE CHORRO DE ARENA C/ACC. | HORA | 3.000000 | $2.78 | $8.34 |
03-4322 | EQUIPO PARA APLICACION DE PINTURA POR ASPERSION C/ACC. | HORA | 3.000000 | $1.72 | $5.16 |
03-4300 | COMPRESOR PORTATIL | HORA | 3.000000 | $167.50 | $502.50 |
Suma de Equipo | $527.73 | ||||
Costo Directo | $3,800.72 |