| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 70-1240 | RASQUETEO CEPILLADO Y LIMPIEZA MANUAL DE SUPERFICIES METALICAS EN TUBERIAS DE PROCESO DE 2" A 6" Y DE 0.00 A 5.00 M. DE ALTURA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 2601-40 | THINER | LT | 0.200000 | $16.50 | $3.30 |
| 2601-55 | ESTOPA | KG | 0.020000 | $11.93 | $0.24 |
| 1652-64 | DETERGENTE EN POLVO | KG | 0.090000 | $12.21 | $1.10 |
| 0308-10 | TORRE DE TRABAJO DE 6 M DE ALTURA CON RUEDAS | R/D | 0.050000 | $78.33 | $3.92 |
| Suma de Material | $8.56 | ||||
| Mano de Obra | |||||
| 02-0020 | CUADRILLA No 2 ( 2 PEONES ) | JOR | 0.025000 | $573.45 | $14.34 |
| Suma de Mano de Obra | $14.34 | ||||
| Costo Directo | $22.90 |