| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 07-1770 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 20 X 30 CM, CONCRETO F'C=200 KG/CM2-3/4", REFORZADA CON 4 VARILLAS R.N. DE 1/2" ESTRIBOS DE 1/4" A/C 25 CM | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.962000 | $12.74 | $25.00 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 4.183200 | $10.43 | $43.63 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 1.106900 | $12.55 | $13.89 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $14.23 | $2.85 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $18.93 | $2.56 |
| 0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
| Suma de Material | $91.18 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.148100 | $756.84 | $112.09 |
| Suma de Mano de Obra | $112.09 | ||||
| Concepto | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.063000 | $981.58 | $61.84 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.148100 | $22.08 | $3.27 |
| Suma de Concepto | $65.11 | ||||
| Costo Directo | $268.38 |