Clave | Descripción del Análisis de Precio Unitario | Unidad |
06-1010 | COLUMNA EN ESTRUCTURA INCLUYE CIMBRA Y DESCIMBRA SECCION=20 X 30 CM CIMBRA COMUN REFORZADA CON 180 KG/M3 ACERO FY’=4200 KG/CM2 CONCRETO F’C=200 KG/CM2-3/4″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Concepto | |||||
05-1090 | CIMBRA COMUN EN COLUMNAS DE 20 X 30 CM. | M2 | 16.666600 | $209.16 | $3,485.99 |
05-3230 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 Nº 5 DIAMETRO 5/8″ | TON | 0.153000 | $15,178.29 | $2,322.28 |
05-3170 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 Nº 2 DIAMETRO 1/4″ | TON | 0.027000 | $19,524.93 | $527.17 |
05-5730 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F’C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4″ EN COLUMNAS Y MUROS | M3 | 1.000000 | $1,482.18 | $1,482.18 |
Suma de Concepto | $7,817.62 | ||||
Costo Directo | $7,817.62 |