Clave | Descripción del Análisis de Precio Unitario | Unidad |
09-2610 | PISO DE CONCRETO EN CUADROS ARISTAS REMATADAS CON VOLTEADOR CUADROS DE 2.00 X 1.80 M ESPESOR=4 CM CONCRETO HECHO EN OBRA F’C=150 KG/CM2-3/4″ REFUERZO=MALLA 66-1010 ACABADO=SIN ACABADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $14.39 | $14.68 |
Suma de Material | $16.37 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.129000 | $756.84 | $97.63 |
Suma de Mano de Obra | $97.63 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.041600 | $912.50 | $37.96 |
Suma de Concepto | $37.96 | ||||
Costo Directo | $151.96 |