| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 09-2300 | PISO DE CONCRETO ARMADO DE 10 CM DE ESPESOR CONCRETO HECHO EN OBRA F'C=100 KG/CM2, AGREGADO MAXIMO 1 1/2" REFUERZO = MALLA 66-1010 ACABADO PULIDO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $14.39 | $14.68 |
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
| Suma de Material | $16.37 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $756.84 | $94.61 |
| Suma de Mano de Obra | $94.61 | ||||
| Concepto | |||||
| 03-2150 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.104000 | $801.96 | $83.40 |
| Suma de Concepto | $83.40 | ||||
| Costo Directo | $194.38 |