Clave | Descripción del Análisis de Precio Unitario | Unidad |
06-8320 | FABRICACION Y MONTAJE HASTA 20 METROS DE ALTURA DE ESTRUCTURA METALICA CON PERFILES MON-TEN PTR | KG |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0128-02 | PERFILES MON-TEN 4″ | TON | 0.001100 | $17,531.57 | $19.28 |
0128-03 | ANGULO Y SOLERA COMERCIAL A-36 | TON | 0.000100 | $16,641.88 | $1.66 |
1551-30 | SOLDADURA E-6013 DE 1/8″ | KG | 0.030000 | $56.18 | $1.69 |
2600-95 | PINTURA ANTICORROSIVA ( PRIMER ) COMEX | LT | 0.007000 | $43.98 | $0.31 |
2000-62 | GRUA, PLUMA, POLEAS Y CABLE | R/D | 0.003300 | $197.97 | $0.65 |
0308-25 | TORRE DE TRABAJO DE 12 M DE ALTURA CON RUEDAS | R/D | 0.003300 | $140.54 | $0.46 |
Suma de Material | $24.05 | ||||
Mano de Obra | |||||
02-0810 | CUADRILLA No 81 ( 1 SOLDADOR CALIFICADO + 2 SOLDADORES + 3 AYUDANTES ) | JOR | 0.014200 | $2,373.64 | $33.71 |
Suma de Mano de Obra | $33.71 | ||||
Costo Directo | $57.76 |