Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-1690 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 20 X 25 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.902100 | $12.74 | $24.23 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.162800 | $12.58 | $14.63 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 1.105400 | $12.55 | $13.87 |
0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $14.23 | $2.85 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $18.93 | $2.56 |
0950-05 | DIESEL | LT | 0.600000 | $5.41 | $3.25 |
Suma de Material | $61.39 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.142800 | $756.84 | $108.08 |
Suma de Mano de Obra | $108.08 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.052500 | $981.58 | $51.53 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.142800 | $22.08 | $3.15 |
Suma de Concepto | $54.68 | ||||
Costo Directo | $224.15 |