Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-0210 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 15 CM, CONCRETO F’C=150 KG/CM2-3/4″, REFORZADA CON ARMEX DE 15 X 15-4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106000 | $12.74 | $14.09 |
0110-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 15 – 4 | M | 1.050000 | $24.41 | $25.63 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $18.93 | $2.37 |
0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
Suma de Material | $47.11 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.072700 | $756.84 | $55.02 |
Suma de Mano de Obra | $55.02 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.023600 | $912.50 | $21.54 |
Suma de Concepto | $21.54 | ||||
Costo Directo | $123.67 |