Clave | Descripción del Análisis de Precio Unitario | Unidad |
05-1080 | CIMBRA COMUN EN CONTRATRABES DE CIMENTACION DE 25 X 100 CM. | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 2.900000 | $12.74 | $36.95 |
1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2″ X 4″ | PT | 1.910000 | $12.74 | $24.33 |
1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 3 1/2″ X 3 1/2″ | PT | 1.050000 | $6.25 | $6.56 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.090000 | $18.93 | $1.70 |
0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2″ ) | KG | 1.000000 | $10.43 | $10.43 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.040000 | $14.30 | $0.57 |
0950-05 | DIESEL | LT | 0.500000 | $5.41 | $2.71 |
Suma de Material | $83.25 | ||||
Mano de Obra | |||||
02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | JOR | 0.144300 | $768.29 | $110.86 |
Suma de Mano de Obra | $110.86 | ||||
Costo Directo | $194.11 |