Clave | Descripción del Análisis de Precio Unitario | Unidad |
40-1490 | SUMINISTRO Y COLOCACION DE COPLE DE BRONCE PARA CONEXION INTERIOR COBRE A ROSCA INTERIOR 100 MM | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
3004-94 | COPLE DE BRONCE P/CONEX. INTERIOR COBRE A ROSCA INT. 100 MM | PZA | 1.010000 | $506.90 | $511.97 |
3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.036800 | $33.60 | $1.24 |
3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.007600 | $52.30 | $0.40 |
3037-34 | GASOLINA BLANCA | LT | 0.139000 | $7.82 | $1.09 |
1502-70 | SEGUETA DE ACERO | PZA | 0.114000 | $7.94 | $0.91 |
3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.053000 | $4.08 | $0.22 |
3035-56 | CINTA TEFLON DE 25 MM | M | 0.515000 | $5.76 | $2.97 |
Suma de Material | $518.80 | ||||
Mano de Obra | |||||
02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.250000 | $802.68 | $200.67 |
Suma de Mano de Obra | $200.67 | ||||
Costo Directo | $719.47 |