Clave | Descripción del Análisis de Precio Unitario | Unidad |
03-2470 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL F’C=200 KG/CM2 AGREGADO MAXIMO 3/4″ CON ADITIVO INCLUSOR DE AIRE | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.368000 | $1,694.85 | $623.70 |
0302-20 | ARENA | M3 | 0.531000 | $157.59 | $83.68 |
0302-30 | GRAVA | M3 | 0.643000 | $157.59 | $101.33 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.252000 | $18.39 | $4.63 |
0171-15 | AIRCON, INCLUSOR DE AIRE PARA CONCRETO | CUB | 0.232400 | $46.35 | $10.77 |
Suma de Material | $824.11 | ||||
Mano de Obra | |||||
02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
Suma de Mano de Obra | $162.69 | ||||
Equipo | |||||
03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
Suma de Equipo | $5.55 | ||||
Costo Directo | $992.35 |