Clave | Descripción del Análisis de Precio Unitario | Unidad |
03-2260 | CONCRETO HECHO EN OBRA F’C=350 KG/CM2, RESISTENCIA RAPIDA AGREGADO MAXIMO 1 1/2″ | M3 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.479000 | $1,694.85 | $811.83 |
0302-20 | ARENA | M3 | 0.455000 | $157.59 | $71.70 |
0302-30 | GRAVA | M3 | 0.740000 | $157.59 | $116.62 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.293000 | $18.39 | $5.39 |
0173-55 | FESTERMIX R.R. | CUB | 0.482600 | $271.41 | $130.98 |
Suma de Material | $1,136.52 | ||||
Mano de Obra | |||||
02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $2,442.79 | $162.69 |
Suma de Mano de Obra | $162.69 | ||||
Equipo | |||||
03-4050 | REVOLVEDORA MIPSA-KOHLER R-10 8 H.P. 1 SACO | HORA | 0.533300 | $10.41 | $5.55 |
Suma de Equipo | $5.55 | ||||
Costo Directo | $1,304.76 |