| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 040789 | Reducci贸n bushing de fierro negro cedula 40 de 64 x 38 mm, suministro y colocaci贸n. | pza |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MAS749 | Reducci贸n bushing de fierro negro c茅dula 40 de 64 x 38 mm | pza | 1.050000 | $95.91 | $100.71 |
| MAS696 | Permatex | pza | 0.034300 | $17.10 | $0.59 |
| Suma de Material | $101.30 | ||||
| Mano de Obra | |||||
| 01-1238 | Oficial plomero | jor | 0.153800 | $523.85 | $80.57 |
| 01-1123 | Ayudante | jor | 0.153800 | $295.38 | $45.43 |
| Suma de Mano de Obra | $126.00 | ||||
| Herramienta | |||||
| MDI | Mando Intermedio | (%)mo | 0.075000 | $126.00 | $9.45 |
| HES | Herramienta menor | (%)mo | 0.030000 | $126.00 | $3.78 |
| EQS | Seguridad, protecci贸n e higiene | (%)mo | 0.020000 | $126.00 | $2.52 |
| Suma de Herramienta | $15.75 | ||||
| Costo Directo | $243.05 |