Planta de cribado Telsmith vibro King PT 6’x16′ 3 pisos 25 HP alim 30’x42′ 10HP T R inf 25″x36′ 10HP tr LAT.25″X24’7.5 HP

Clave Descripción del costo horario Unidad
CHC76 Planta de cribado Telsmith vibro King PT 6’x16′ 3 pisos 25 HP alim 30’x42′ 10HP T R inf 25″x36′ 10HP tr LAT.25″X24’7.5 HP hr
DATOS GENERALES
Vad = VALOR DE ADQUISICIÓN $2,200,829.02 Pnom = POTENCIA NOMINAL 0 H.P.
Pn = VALOR DE LAS LLANTAS $0.00 Fo = FACTOR DE OPERACION 0
Pa = VALOR DE PIEZAS ESPECIALES $0.00 TIPO DE COMBUSTIBLE Diesel
Vm = VALOR NETO $2,200,829.02 Cco = COEFICIENTE DE COMBUSTIBLE 0.1514
Vr = VALOR DE RESCATE $440,165.80 Pc = PRECIO DEL COMBUSTIBLE /LITRO
i = TASA DE INTERES 16.000000 /AÑO Cc = CAPACIDAD DEL CARTER 0.00 LITROS
s = PRIMA DE SEGUROS 3.000000 /AÑO Tc = TIEMPO ENTRE CAMBIO DE ACEITE 0 HORAS
Ko = FACTOR DE MANTENIMIENTO 0.700000 HORAS Fl = FACTOR DE LUBRICANTE 0.0095
Ve = VIDA ECONÓMICA 14,400.00 HORAS Pac = PRECIO DEL ACEITE /LITRO
Vn = VIDA ECONÓM. DE LAS LLANTAS 4,000.00 HORAS Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom 0 LITROS/HORA
Va = VIDA ECONOM. PIEZAS ESPECIALES 1,000.00 HORAS Ah=CANTIDAD DE LUBRICANTE = Fl*Fo*Pnom 0.000000 LITROS/HORA
Hea = HORAS TRABAJADAS POR AÑO 1,200.00 HORAS Ga=CONSUMO ENTRE CAMBIOS DE LUBRICANTE = Cc/Tc 0.000000 LITROS/HORA
Ht = Horas por turno 6.400000 Ht = HORAS
CONCEPTO OPERACIONES ACTIVO EN ESPERA EN RESERVA
COSTOS FIJOS
DEPRECIACIÓN (D) = (Vm-Vr)/Ve (2200829.02-440165.80)/14400.00 $122.27 $97.82 $97.82
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i [(2200829.02+440165.80)/(2*1200.00)]0.160000 $176.07 $176.07 $176.07
SEGURO (Sm) = [(Vm+Vr)/2Hea]s [(2200829.02+440165.80)/(2*1200.00)]0.030000 $33.01 $33.01 $33.01
MANTENIMIENTO (Mn) = Ko * D 0.700000*122.27 $85.59 $85.59 $68.47
Costos fijos $416.94 $392.49 $375.37
CARGOS POR CONSUMO
COMBUSTIBLE Co = GhxPc 0*0 $0.00 $0.00 $0.00
OTRAS FUENTES DE ENERGÍA 0*0 $0.00 $0.00 $0.00
LUBRICANTES Lb = (Ah+Ga)Pac (0+0)0 $0 $0 $0
LLANTAS = Pn/Vn 0/4000.00 $0.00 $0.00 $0.00
PIEZAS ESPECIALES = Pa/Va 0/1000.00 $0.00 $0.00 $0.00
Cargos por consumo $0.00 $0.00 $0.00
CARGOS POR OPERACIÓN
CATEGORÍA CANTIDAD SALARIO REAL Ht ACTIVO EN ESPERA EN RESERVA
Ayudante 1 $295.38 6.400000 $46.15 $0.00 $0.00
Operador de planta de primera 1 $523.85 6.400000 $81.85 $0.00 $0.00
SUMA (Sr) $819.23 6.400000 $128.00 $0.00 $0.00
Cargos por operación (Sr/Ht) $128.00 $0 $0
Costo Directo por Hora $544.94 $392.49 $375.37

Página  [tcb_pagination_current_page]  de  [tcb_pagination_total_pages]


×