Bomba Warner motor Briggs-Straton 18HP mod. 30m de 4″ x 4″ gasto 151 m3/h

Clave Descripción del costo horario Unidad
CHC48 Bomba Warner motor Briggs-Straton 18HP mod. 30m de 4″ x 4″ gasto 151 m3/h hr
DATOS GENERALES
Vad = VALOR DE ADQUISICIÓN $80,041.24 Pnom = POTENCIA NOMINAL 18.000000 H.P.
Pn = VALOR DE LAS LLANTAS $0.00 Fo = FACTOR DE OPERACION 1.0000
Pa = VALOR DE PIEZAS ESPECIALES $0.00 TIPO DE COMBUSTIBLE Gasolina
Vm = VALOR NETO $80,041.24 Cco = COEFICIENTE DE COMBUSTIBLE 0.1
Vr = VALOR DE RESCATE $20,010.31 Pc = PRECIO DEL COMBUSTIBLE $10.70 /LITRO
i = TASA DE INTERES 16.000000 /AÑO Cc = CAPACIDAD DEL CARTER 0.00 LITROS
s = PRIMA DE SEGUROS 3.000000 /AÑO Tc = TIEMPO ENTRE CAMBIO DE ACEITE 0 HORAS
Ko = FACTOR DE MANTENIMIENTO 0.410000 HORAS Fl = FACTOR DE LUBRICANTE 0.0015
Ve = VIDA ECONÓMICA 2,250.00 HORAS Pac = PRECIO DEL ACEITE $48.28 /LITRO
Vn = VIDA ECONÓM. DE LAS LLANTAS 0.00 HORAS Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom 1.800000 LITROS/HORA
Va = VIDA ECONOM. PIEZAS ESPECIALES 0.00 HORAS Ah=CANTIDAD DE LUBRICANTE = Fl*Fo*Pnom 0.027000 LITROS/HORA
Hea = HORAS TRABAJADAS POR AÑO 750.00 HORAS Ga=CONSUMO ENTRE CAMBIOS DE LUBRICANTE = Cc/Tc 0.000000 LITROS/HORA
Ht = Horas por turno 6.400000 Ht = HORAS
CONCEPTO OPERACIONES ACTIVO EN ESPERA EN RESERVA
COSTOS FIJOS
DEPRECIACIÓN (D) = (Vm-Vr)/Ve (80041.24-20010.31)/2250.00 $26.68 $21.34 $21.34
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i [(80041.24+20010.31)/(2*750.00)]0.160000 $10.67 $10.67 $10.67
SEGURO (Sm) = [(Vm+Vr)/2Hea]s [(80041.24+20010.31)/(2*750.00)]0.030000 $2.00 $2.00 $2.00
MANTENIMIENTO (Mn) = Ko * D 0.410000*26.68 $10.94 $10.94 $8.75
Costos fijos $50.29 $44.95 $42.76
CARGOS POR CONSUMO
COMBUSTIBLE Co = GhxPc 1.800000*10.70 $19.26 $5.78 $0.00
OTRAS FUENTES DE ENERGÍA 0*0 $0.00 $0.00 $0.00
LUBRICANTES Lb = (Ah+Ga)Pac (0.027000+0)48.28 $1.30 $0.39 $0
LLANTAS = Pn/Vn 0/0 $0.00 $0.00 $0.00
PIEZAS ESPECIALES = Pa/Va 0/0 $0.00 $0.00 $0.00
Cargos por consumo $20.56 $6.17 $0.00
CARGOS POR OPERACIÓN
CATEGORÍA CANTIDAD SALARIO REAL Ht ACTIVO EN ESPERA EN RESERVA
Operador de equipo menor 1 $471.88 6.400000 $73.73 $0.00 $0.00
SUMA (Sr) $471.88 6.400000 $73.73 $0.00 $0.00
Cargos por operación (Sr/Ht) $73.73 $0 $0
Costo Directo por Hora $144.58 $51.12 $42.76