Clave | Descripción del Análisis de Precio Unitario | Unidad |
SARDI011 | Sardinel de 15 x 9 cms de concreto simple f’c=150 kg/cm2, incluye: material, mano de obra y herramienta. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01VAR003 | VARILLA CORRUGADA DE 3/8″ | KG | 0.640050 | $8.60 | $5.50 |
17AZU010 | AZULEJO ANTIDERRAPANTE 20 X 20 CMS | M2 | 0.550000 | $99.19 | $54.55 |
06MAD001 | MADERA DE PINO | PT | 0.100000 | $10.00 | $1.00 |
Suma de Material | $61.05 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.200000 | $401.97 | $80.39 |
MOA05004 | P E O N | JOR | 0.200000 | $210.17 | $42.03 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $122.42 | $6.12 |
Suma de Mano de Obra | $128.54 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $122.42 | $2.45 |
Suma de Herramienta | $2.45 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.014180 | $1,185.15 | $16.81 |
BASIP003 | PASTA PEGAZULEJO-AGUA | M3 | 0.002900 | $4,213.40 | $12.22 |
BASIL001 | LECHADA DE CEMENTO BLANCO | M3 | 0.000600 | $6,186.05 | $3.71 |
Suma de Auxiliar | $32.74 | ||||
Costo Directo | $224.78 |