| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| TEE00001 | Tee de cobre de 1/2", incluye: suministro y colocaci贸n. | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 08TEE001 | TEE DE COBRE DE 1/2" | PZA | 1.020000 | $6.11 | $6.23 |
| 12LIJ000 | L I J A | PZA | 0.120000 | $7.00 | $0.84 |
| 08PAS000 | PASTA FUNDENTE PARA SOLDAR 250 GRS. | PZA | 0.120000 | $34.59 | $4.15 |
| 08SOL000 | SOLDADURA DE ESTA脩O 50 X 50 | ROL | 0.120000 | $42.77 | $5.13 |
| Suma de Material | $16.35 | ||||
| Mano de Obra | |||||
| MOP05002 | OFICIAL PLOMERO | JOR | 0.025000 | $401.97 | $10.05 |
| MOA05003 | AYUDANTE | JOR | 0.025000 | $245.43 | $6.14 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $16.19 | $0.81 |
| Suma de Mano de Obra | $17.00 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $16.19 | $0.32 |
| Suma de Herramienta | $0.32 | ||||
| Costo Directo | $33.67 |