Clave | Descripción del Análisis de Precio Unitario | Unidad |
PISO0050 | Piso de concreto estampado de 50 x 90 cms y espesor de 8.0 cms para andador peatonal, incluye: fabricacion y colocacion. | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
06MAD001 | MADERA DE PINO | PT | 0.540000 | $10.00 | $5.40 |
13DIE000 | DIESEL | LT | 0.027000 | $7.00 | $0.19 |
06CLA001 | CLAVOS | KG | 0.011250 | $18.00 | $0.20 |
02CEM000 | CEMENTO GRIS | KG | 0.675000 | $2.40 | $1.62 |
Suma de Material | $7.41 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.125000 | $401.97 | $50.25 |
MOA05004 | P E O N | JOR | 0.125000 | $210.17 | $26.27 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $76.52 | $3.83 |
Suma de Mano de Obra | $80.35 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $76.52 | $1.53 |
Suma de Herramienta | $1.53 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.037800 | $1,185.15 | $44.80 |
BASIC000 | CURADO CON CURACRETO | M2 | 0.450000 | $4.01 | $1.80 |
Suma de Auxiliar | $46.60 | ||||
Costo Directo | $135.89 |