| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| POZOV014 | Pozo de visita tipo com煤n, profundidad de 1.45 mts. a base de tabique 7x14x28 cms. asentado y aplanado con mortero cemento-arena 1:3, incluye: excavaci贸n a m谩quina, relleno, compactaci贸n, materiales y mano de obra. | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 01VAR005 | VARILLA CORRUGADA DE 5/8" | KG | 2.625000 | $8.60 | $22.58 |
| 02CEM000 | CEMENTO GRIS | KG | 2.400000 | $2.40 | $5.76 |
| 19TAB005 | TABIQUE ROJO RECOCIDO | PZA | 640.000000 | $2.10 | $1,344.00 |
| 03ARE000 | ARENA | M3 | 0.731600 | $130.01 | $95.12 |
| Suma de Material | $1,467.46 | ||||
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBA脩IL 1RA. | JOR | 1.666670 | $401.97 | $669.95 |
| MOA05004 | P E O N | JOR | 3.333330 | $210.17 | $700.57 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.100000 | $1,370.52 | $137.05 |
| Suma de Mano de Obra | $1,507.57 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $1,370.52 | $68.53 |
| Suma de Herramienta | $68.53 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.480000 | $1,185.15 | $568.87 |
| BASIM003 | MEZCLA CEMENTO-ARENA 1:3 | M3 | 0.600000 | $1,510.95 | $906.57 |
| Suma de Auxiliar | $1,475.44 | ||||
| Concepto | |||||
| EXCAV002 | EXCAVACION A MAQUINA EN MATERIAL TIPO "B" SECCION OBLIGADA CON RETROEXCAVADORA. | M3 | 4.800000 | $34.25 | $164.40 |
| CARGA001 | CARGA MEC脕NICA Y ACARREO EN CAMI脫N VOLTEO DE MATERIAL TIPO I Y II PRODUCTO DE MATERIAL SOBRANTE HASTA EL PRIMER KM. DE DISTANCIA, VOLUMEN MEDIDO EN BANCO. | M3 | 6.800000 | $20.23 | $137.56 |
| RELLE002 | RELLENO EN ZANJAS COMPACTADO AL 95% PVSM EN CAPAS DE 20 CMS. CON MATERIAL PRODUCTO DE EXCAVACI脫N. INCLUYE: PAPEO DEL MATERIAL, ACARREO PARA SU COLOCACI脫N, MANO DE OBRA, EQUIPO Y HERRAMIENTA. | M3 | 2.980000 | $120.31 | $358.52 |
| Suma de Concepto | $660.48 | ||||
| Costo Directo | $5,179.48 |