| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CAST0031 | Castillo ahogado en hueco de block de 20 cms, a base de concreto f'c=150 kg/cm2, sin armado, incluye: material, mano de obra y herramienta. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 06MAD001 | MADERA DE PINO | PT | 0.020000 | $10.00 | $0.20 |
| Suma de Material | $0.20 | ||||
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.017900 | $401.97 | $7.20 |
| MOF05001 | OFICIAL FIERRERO | JOR | 0.005500 | $401.97 | $2.21 |
| MOA05003 | AYUDANTE | JOR | 0.009900 | $245.43 | $2.43 |
| MOA05004 | P E O N | JOR | 0.017900 | $210.17 | $3.76 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $15.60 | $0.78 |
| Suma de Mano de Obra | $16.38 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $15.60 | $0.31 |
| Suma de Herramienta | $0.31 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.026900 | $1,185.15 | $31.88 |
| Suma de Auxiliar | $31.88 | ||||
| Costo Directo | $48.77 |