Clave | Descripción del Análisis de Precio Unitario | Unidad |
RAMEL040 | Ramaleo eléctrico, incluye: materiales, resanes, mano de obra y herramienta. | LOTE |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
11POL003 | POLIDUCTO NARANJA DE 3/4″ | ML | 13.000000 | $1.53 | $19.89 |
11POL002 | POLIDUCTO NARANJA DE 1/2″ | ML | 114.000000 | $1.40 | $159.60 |
11CEN004 | CENTRO DE CARGA QO-4 SQUARE-D | PZA | 1.000000 | $134.03 | $134.03 |
11CAJ002 | CAJA CHALUPA GALVANIZADA DE 2″ X 4″ | PZA | 12.000000 | $2.06 | $24.72 |
11CAJ003 | CAJA HEXAGONAL GALVANIZADA DE 3″ X 3″ | PZA | 9.000000 | $2.06 | $18.54 |
11TUB001 | TUBO CONDUIT GALVANIZADO DE 1/2″ | ML | 1.500000 | $6.51 | $9.77 |
11MUF001 | MUFA GALVANIZADA DE 1/2″ | PZA | 2.000000 | $7.66 | $15.32 |
11CON100 | CONTRA Y MONITOR GALVANIZADOS DE 13 MM | PZA | 2.000000 | $1.55 | $3.10 |
11CON200 | CONECTOR GALVANIZADO DE 1/2″ | PZA | 2.000000 | $2.05 | $4.10 |
Suma de Material | $389.07 | ||||
Mano de Obra | |||||
MOE05001 | OFICIAL ELECTRICISTA | JOR | 1.000000 | $401.97 | $401.97 |
MOA05003 | AYUDANTE | JOR | 1.000000 | $245.43 | $245.43 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $647.40 | $32.37 |
Suma de Mano de Obra | $679.77 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $647.40 | $12.95 |
Suma de Herramienta | $12.95 | ||||
Costo Directo | $1,081.79 |