| Material | | | | |
| 24TAP006 | TAPA Y MARCO METALICOS DE 60 X 60 CMS | PZA | 1.030000 | $600.02 | $618.02 |
| 01VAR008 | VARILLA CORRUGADA DE 1" | KG | 12.000000 | $8.60 | $103.20 |
| Suma de Material | | | | $721.22 |
| Mano de Obra | | | | |
| MOA05001 | OFICIAL ALBA脩IL 1RA. | JOR | 0.500000 | $401.97 | $200.99 |
| MOA05004 | P E O N | JOR | 0.500000 | $210.17 | $105.09 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.100000 | $306.08 | $30.61 |
| Suma de Mano de Obra | | | | $336.69 |
| Herramienta | | | | |
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $306.08 | $15.30 |
| Suma de Herramienta | | | | $15.30 |
| Concepto | | | | |
| EXCAV002 | EXCAVACION A MAQUINA EN MATERIAL TIPO "B" SECCION OBLIGADA CON RETROEXCAVADORA. | M3 | 22.500000 | $34.25 | $770.63 |
| CARGA001 | CARGA MEC脕NICA Y ACARREO EN CAMI脫N VOLTEO DE MATERIAL TIPO I Y II PRODUCTO DE MATERIAL SOBRANTE HASTA EL PRIMER KM. DE DISTANCIA, VOLUMEN MEDIDO EN BANCO. | M3 | 13.824000 | $20.23 | $279.66 |
| RELLE002 | RELLENO EN ZANJAS COMPACTADO AL 95% PVSM EN CAPAS DE 20 CMS. CON MATERIAL PRODUCTO DE EXCAVACI脫N. INCLUYE: PAPEO DEL MATERIAL, ACARREO PARA SU COLOCACI脫N, MANO DE OBRA, EQUIPO Y HERRAMIENTA. | M3 | 8.676000 | $120.31 | $1,043.81 |
| AFINE002 | AFINE A MANO DE EXCAVACIONES REALIZADAS CON MAQUINARIA, INCLUYE: MANO DE OBRA Y HERRAMIENTA. | M2 | 15.360000 | $11.25 | $172.80 |
| CIM00009 | CIMBRA COM脷N EN CIMENTACI脫N, INCLUYE: HABILITADO, CIMBRADO Y DESCIMBRADO, MEDIDO POR SUPERFICIE DE CONTACTO. | M2 | 1.920000 | $215.28 | $413.34 |
| ACERO003 | ACERO DE REFUERZO DE 3/8" EN CIMENTACION, INCLUYE: SUMINISTRO, COLOCACION, FLETES, TRASLAPES, CORTES Y DESPERDICIOS. | KG | 54.432000 | $16.78 | $913.37 |
| CONC0107 | CONCRETO PREMEZCLADO PARA CIMENTACION, F'C=250 KG/CM2, T.M.A. 3/4", REVENIMIENTO DE 14 CMS, BOMBEABLE, INCLUYE: SUMINISTRO, BOMBEO DE CONCRETO, COLADO, VIBRADO Y CURADO. | M3 | 1.152000 | $1,390.16 | $1,601.46 |
| CIM00014 | CIMBRA APARENTE DE MUROS DE CONCRETO, INCLUYE: HABILITADO, CIMBRADO Y DESCIMBRADO, MEDIDO POR SUPERFICIE DE CONTACTO. | M2 | 39.040000 | $157.71 | $6,157.00 |
| CONC0117 | CONCRETO PREMEZCLADO PARA MUROS, F'C=200 KG/CM2, T.M.A. 3/4", REVENIMIENTO DE 18 CMS, BOMBEABLE, CON IMPERMEABILIZANTE INTEGRAL AL 2%, INCLUYE: SUMINISTRO, BOMBEO DE CONCRETO, COLADO, VIBRADO Y CURADO. | M3 | 3.520000 | $1,400.21 | $4,928.74 |
| CIM00028 | CIMBRA APARENTE DE LOSA DE ENTREPISO, INCLUYE: HABILITADO, CIMBRADO Y DESCIMBRADO, MEDIDO POR SUPERFICIE DE CONTACTO. | M2 | 5.920000 | $154.23 | $913.04 |
| ACERO013 | ACERO DE REFUERZO DE 3/8" EN ESTRUCTURA DE PLANTA BAJA, INCLUYE: SUMINISTRO, COLOCACION, FLETES, TRASLAPES, CORTES Y DESPERDICIOS. | KG | 54.432000 | $16.78 | $913.37 |
| CONC0133 | CONCRETO PREMEZCLADO PARA LOSAS Y TRABES, F'C=250 KG/CM2, T.M.A. 3/4", REVENIMIENTO DE 14 CMS, BOMBEABLE, INCLUYE: SUMINISTRO, BOMBEO DE CONCRETO, COLADO, VIBRADO Y CURADO. | M3 | 1.152000 | $1,400.21 | $1,613.04 |
| Suma de Concepto | | | | $19,720.26 |
| Costo Directo | | | | $20,793.47 |